32.5%
Overall coverage
496 / 1,522 km acquired
15.997
km acquired today
5 lines · DPR #38
6:46
Fisheries standby (total)
8 entanglements · 0 today
38
Days without incident
No recordable incidents
35
BBSO cards
1 open · project to date
3,684
Man-hours
96 hrs today · POB 8
Time breakdown — project to date
Operations842.5 h (55.8%)
Transit310.0 h (20.5%)
Standby — weather128.5 h (8.5%)
Mobilisation96.0 h (6.4%)
Equipment downtime22.5 h (1.5%)
Standby — fisheries6.8 h (0.4%)
Area coverage — top blocks today
| Area | Planned km | Progress | Today |
|---|---|---|---|
| M12 | 48.0 | 20.2% | +4 lines |
| M20 | 138.7 | 22.9% | +1 line |
| INF | 13.3 | 100% | +6 infills |
| M16 | 47.1 | 100% | – |
| P2 | 73.1 | ~100% | – |
| M13 | 90.1 | 66.6% | – |
| M17 | 193.6 | 17.4% | – |
| M18 | 81.5 | 14.2% | – |
| TIE | 75.2 | 0% | – |
Vessel status — DPR #38
Fuel today
52 galFuel remaining
187 galFuel project total
1,699 galAvg gal/day
44.7Trash today
4 kgPOB
8Weather — 2025-03-30
| Time (local) | Wind | Seas |
|---|---|---|
| 08:00 | SW 15 kts | 2 ft |
| 12:00 | W 18 kts | 3 ft |
| 16:00 | W 14 kts | 2 ft |
| 20:00 | NW 10 kts | 1 ft |
Forecast: W 10–15 kts easing. Seas 1–2 ft. Good survey conditions expected.
Recent DPR activity
2025-03-30
DPR #38 — 4 lines M12, 1 line M20, 6 infills
15.997 km · EDT 1.0 h (SSS dropout)
2025-03-29
DPR #37 — M11 complete, transit
10.5 h ops · Approved
2025-03-28
DPR #36 — Standby weather AM, ops PM
6.0 h ops · 4.0 h Stby.W
2025-03-27
DPR #35 — M10 x4, M10 x4
11.0 h ops · Submitted
2025-03-26
DPR #34 — M10 mainlines
10.0 h ops · Approved
Sensor acceptance — today
Lines acquired 2025-03-30 · Area M12
MBES
All lines accepted
SSS
1 line pending QC (M1202_01)
SBP
All lines accepted
TVG
Infill flagged — M1203_01
UHRS
N/A today
Outstanding requirements
M1203_01TVG infill
M1003_01SBP infill
M1302_01SSS rerun
I3103_01Fishing gear blocking
Open actions 1 item
BBSO — Open
BSO-ASW01-035: Single winch operation without radio confirmation from party chief.
Submitted 2025-03-28 · Follow-up: JSA update required
Infill — Fishing gear blocking
I3103_01 and I3602_01 — gear still present in corridor. Party chief comments DPR #38.
Logged 2025-03-30 · FAL-009 · Scout vessel required
DWI — 38 days ✓
No recordable incidents. 4 incidents closed. 6 corrective actions — all closed.
32.5%
Overall coverage
496.1 km
Virgin lines acquired
6.1 km
Infill acquired
1.3 km
Rerun acquired
Block-by-block coverage
| Area | Type | Planned km | Acquired km | Infill | Rerun | Coverage | Lines today | Remaining km |
|---|---|---|---|---|---|---|---|---|
| Total | 1,522.3 | 496.1 | 6.1 | 1.3 | 32.5% | 11 | 1,026.2 | |
Lines requiring action
| Line ID | Area | Issue | Sensor | Priority | Notes |
|---|---|---|---|---|---|
| M1203_01 | M12 | Infill req. | TVG | Medium | Alt out of spec — floated for shallow water |
| M1302_01 | M13 | Rerun req. | SSS | High | SSS mosaic gap >5m — full rerun required |
| M1003_01 | M10 | Infill req. | SBP | Medium | SBP penetration <20m |
| I3103_01 | M13 | Gear blocking | All | Medium | Gill net present — scout vessel required pre-run |
8
Entanglements
Project to date
6:46
Total downtime
hh:mm fisheries standby
2
VHF contacts
Fishing vessels contacted
4
Course deviations
Remained online
1
Comp. referrals
Under Marine Affairs review
Entanglement register
| Date | Block | Equipment | Dmg survey | Dmg gear | Downtime | Sev. |
|---|---|---|---|---|---|---|
| 2025-08-11 | M15 | TVG | None | None | 0:00 self-rel | Low |
| 2025-08-13 | M11 | All towed | None | None | 04:56 | High |
| 2025-08-29 | INF | UHRS streamer | None | None | 0:00 self-rel | Low |
| 2025-09-01 | M15 | TVG | None | None | 0:25 | Low |
| 2025-09-03 | M11 | SSS/TVG | None | Buoy line broke | 0:12 | Med |
| 2025-10-10 | M19 | SSS | None | None | 0:00 self-rel | Low |
| 2025-10-18 | M18 | SSS/TVG | None | None | 0:00 self-rel | Low |
| 2025-10-22 | M17 | SSS/TVG | None | Buoy parted | 1:13 | Med |
Standby by area
M115:08
M171:13
M150:25
M18 / M190:00
Gear type distribution
SSS/TVG combined5 interactions
Gill net3
Lobster/crab pots3
Ghost gear1
38
Days without incident
HSE headline — project to date
Total man-hours
3,684TBTs completed
38JSAs reviewed
148Drills conducted
10BBSO cards
35Recordable incidents
0Near misses
0PSO observations
7Incident register — summary
| Ref. | Date | Type | Severity | Status |
|---|---|---|---|---|
| INC-ASW01-001 | 2025-08-13 | Equipment damage | Med | Closed |
| INC-ASW01-002 | 2025-10-22 | Equipment damage | Med | Closed |
| INC-ASW01-003 | 2025-12-08 | Safety stand-down | High | Closed |
| INC-ASW01-004 | 2026-02-05 | Equipment damage | Med | Closed |
PSO / marine mammals — project to date
| Species | Obs. | No mit. | Delay | Shutdown |
|---|---|---|---|---|
| Common dolphin | 2 | 1 | 1 | 0 |
| Harbour porpoise | 1 | 0 | 1 | 0 |
| Humpback whale | 1 | 1 | 0 | 0 |
| Bottlenose dolphin | 1 | 1 | 0 | 0 |
| PAM detection | 2 | 0 | 2 | 0 |
| Grey seal | 1 | 1 | 0 | 0 |
| Total | 8 | 4 | 4 | 0 |
Total delay time from soft-start deferrals: 35 minutes
Assessment ratings follow the standard OS framework: Poor / Adequate / Good / Excellent — as used in Mayflower Wind and SBW01 CSR/OS reports. Ratings updated by OS only.
Contractor assessment — Demo Survey Co.
Mobilisation
Equipment performance
Survey crew (online)
Processing crew (offline)
Vessel crew
Vessel performance
HSE culture
HSE documentation
Fisheries management
Data quality
Line planning
Logistics
Overall field operations
OS notes & recommendations
HSE documentation
BBSO tracking still driven by OS. Recommend requiring weekly PDF submission with card status. TBT and JSA reviews to be included in DPR ops diary as standard deliverable.
Infill / rerun log
Coverage analysis QC to be delegated to one designated person. Infill/rerun shapefile to use standardised fields agreed with OS during mobilisation. QGIS layer maintained as single source of record.
Fisheries planning
Gear scouting and daily tracking in nav software significantly improved after Aug. Recommend making this a contractual deliverable from day one on future projects.
Processing crew
24hr deliverables generally on time. Lagged when key personnel absent. Coverage analysis delegation needed. Recommend dedicated QC lead role for future campaigns.
Recommended for future campaigns?
Module links — generate end-of-project report
DPR log
38 DPRs · All submitted
→
Line tracker
496 km · 15 lines pending
→
Fishing activity
12 interactions · 8 entanglements
→
HSE / incidents
4 incidents · all closed
→